Building contractor & Entrepreneurs
Building contractor
The project is owned by Norsk Vind Egersund AS. Norsk Vind Energi AS represents the owners of the project, and will remain as project leaders.

Turbine supplier
The German turbine supplier Senvion will deliver the turbines for the project.

Entrepreneur
Veidekke has the overall responsibility for everything related to infrastructure. This means that it is Veidekke that both plans, and executes, any work related to roadworks, riggings areas, foundations, transformer stations, as well as all electric and technical deliveries of cables and transformers. Veidekke have also brought on-board Berthelsen and Garpestad as sub-contractors for road construction, as well as Otera in relation to powerline and VEO in charge of electrical deliveries.

Poweline entrepeneur
Otera is responsible for constructing the approximately eight kilometers of poweline that will connect the project to the pre-existing Kjelland transformer station.

(Construction of powerlines)

Ongoing construction
The construction of necessary roadworks began August 1st. 2016, and is now in it`s final stages of re-vegetation.

The first transportation of turbine component deliveries to the southern site area started 03.04.17. The commissioning phase of the turbines in the southern site area started at the end of april, and by the end of may in the northern site area.

Location

Egersund Wind Farm is located by Åsheia and Kolldalsheia in the municipality of Eigersund, approximately 5-8 kilometres east of the city of Egersund.

It has been many years since our first thoughts turned to the potential of a wind farm in this area, and we are pleased that all turbines are commisioned and gene‍‍‍rating power!

Further information
If one wants to read further development details and paperwork concerning Egersund Wind Farm, these are readily available at the Norwegian Water Resources and Energy Directorate’s (NVE) webpage.

Egersund wind farm is currently under construction!

Important information:
The main activities on site will now commence inside the turbines, and week by week you will see more tubines rotating. The turbines will start their trial-period once they start rotating. The number of workers will gradually decrease, which will result in less traffic to and from site areas.

By the end of September, clearing activities alongside Hålandsdalen will commence. By October similar activities will be executed alongside Heggdalsveien. We apologize for any inconvenience this may result in for the people who use these roads regularly.

Timeline: (Please note that changes may occur)

I

Construction begins on roadworks and turbine foundations

01.08-16

I

Construction of powerlines complete

01.05-17

Construction of northern roadworks and turbine foundations complete. Transport of first turbines commences.

I

26.05-17

I

Activation of first turbine.

29.05-17

Final turbine transport

I

24.08-17

I

Project complete

21.12-17

Construction begins on the powerlines

I

01.03-16

Construction of southern roadworks and turbine foundations complete

I

31.03-17

Project information

Location

Egersund Wind Farm is located by Åsheia and Kolldalsheia in the municipality of Eigersund, approximately 5-8 kilometres east of the city of Egersund. On the map you can see the project area, highlighted in red, as well as the planned placements of the turbines and roadworks.

Contact information
For more information, please contact our project leader via E-mail or Telephone.

Per Ove Skorpen
Project leader

Mobile: 95 16 00 05
E-mail: skorpen@vind.no

(Construction of roadworks and turbine foundations)

Contact information:

Per Ove Skorpen
Project leader

Mobile: 95 16 00 05

E-mail:
skorpen@vind.no

Progress report
During September 2016, the rigging area was established with temporary pre-fabricated cabins.

The roadworks were completed for turbine transportation by the end April. During this same period all the foundations for the different wind turbines was also finalized, so that these were ready for turbine installation.

The wind turbine commissioning began early in May 2017, and the last turbine components were installed by September 2017.

The whole project should be completed by the end of 2017.

Working hours
The project will be utilizing the following work hours: 7am to 9pm during regular workdays, and 7am to 3pm on Saturdays. No work is to be conducted on Sundays.

The entrepreneurs do not expect the work to cause disproportionate and unnecessary disturbances during these work times, thus avoiding inconveniencing neighboring properties.

Traffic

All transportation of turbine components is now completed. This will result in a considerate reduction in roadside activities. The main activities from this point will consist of de-commissioning of equipment and reconditioning of Hålandsdalen and public roads from late september.

Per Ove Skorpen
Project leader

Mobile: 95 16 00 05

E-mail: skorpen@vind.no

Safety measures measures

We kindly ask people to take care, and recognize that the area in question is experiencing heavy construction work. With this in mind we remind people to prioritize their safety, and refrain from travelling in the area. Warning signs will be placed around the area, and we ask that people respect their message.

Planned magnitude
Egersund Wind Farm will consist of 33 wind turbines, each generating 3.4 MW for a combined effect of 112.2 MW.

The expected annual production should be around 395GWh, which equates to the annual electric consumption of 20.000 Norwegian households.

Projected cost
The construction of Egersund Wind Farm will cost approximately 1.2 billion Norwegian kroner (NOK).

Norsk Vind Energi
Wind power
Clean and renewable

(Construction of powerlines)

(Fundation work and laying of cables)